I-595 flyover ramp nearly raised 18 inches

Published On: Jul 15 2012 04:27:30 PM EDT
Updated On: Jul 16 2012 08:05:25 AM EDT

Crews working to raise the Interstate 595 flyover ramp worked through the day and rain.

FORT LAUDERDALE, Fla. -

Construction crews are nearly finished raising an entire flyover bridge 18 inches into the air using hydraulic jacks as part of the $1.2 billion Interstate 595 Express Lane construction project.

At of 11 p.m. Sunday, a spokesperson for the project said the ramp had been raised nearly 17 inches. The ramp is raised 1 inch each hour.

READ: University Dr. interchange closure

The flyover ramp from southbound University Drive to eastbound I-595 will be closed for 120 days, officials said.

The project will be done in 2014.

Gallery

Construction

PHOTOS: I-595 construction

Click here for more information.

Comments

The views expressed are not those of this company or its affiliated companies. Please note by clicking on "Post" you acknowledge that you have read the Terms Of Service and the comment you are posting is in compliance with such terms. 
blog comments powered by Disqus